A solar power plant going up, in the order it was built — foundations through to transformer placement.
Quick answer
These are site photographs from a solar power plant executed by Enersys Engineers, arranged in construction sequence. Pile foundations and pedestal casting, module mounting structure erection, module installation and DC string cabling, inverter and AC combiner mounting, cable trenching and conduit laying, and the delivery, lifting and placement of the power transformers.
Foundations & piling

Reinforcement cage set against the pile line before pedestal casting.

Pile alignment checked row by row — the geometry every table above it inherits.

Pedestal concreting across the array field.

Pedestals cast and cured ahead of structure erection.

Casting in progress, with the array grid already set out to the horizon.
Civil works & cable routes

Switchgear landed on its plinth, still wrapped against site dust.

Plinth works ahead of equipment placement.

Foundation excavation for the equipment yard.

Trench inspected for depth and line before any cable is pulled.

Cable route cut between the array blocks.

Trenching alongside the array, clear of the table foundations.

Aggregate stockpiled for backfill and earth pits.

Spoil kept clear of the route so backfill goes back clean.

Material run to the trench face by hand where plant cannot reach.

The route back to the inverter station, opened and squared.
Transformer installation

Transformer received on site and checked before lifting.

Rigged from the designated lifting lugs, nothing improvised.

Controlled lift, with the slew path walked beforehand.

Off the trailer and clear.

Second unit waiting its turn on the hardstanding.

Transformer set down onto its plinth, site team standing clear.

Positioned and levelled, ready for terminations.
About this gallery
What does this gallery show?
Work in progress on a solar power plant built by Enersys Engineers, photographed through the construction sequence: pile foundations and pedestal casting, module mounting structure erection, module installation and DC string cabling, inverter and AC combiner mounting, cable trenching and conduit laying, and the delivery, lifting and placement of the power transformers.
Are these Enersys Engineers’ own projects?
Yes. These are site photographs from work executed by Enersys Engineers, not stock photography. Client names and plant capacities are withheld here; a full credential list with references is available on request for prequalification.
Can I see photographs of substation or transmission line work?
More site photography is being added as it is collected. In the meantime the project atlas records twelve milestone projects from 2006 to 2024 across transmission lines, EHV substations, solar and thermal power, including Odisha’s first monopole 132 kV transmission line.